Project Duration
  • 12/2008 - 02/2009
    08/2009 - 10/2009
  • Name of Projects
  • Viet Thuan Thanh Office Building
  • Scope of Works
  • Test pile: Diamater: 1.2(e); Depth: 46.5(e); Quantity: 2
  • Test pile: Diamater: 0.8(e); Depth: 46.5(e); Quantity: 1
  • Bored pile: Diamater: 1.2(e); Depth: 46.5(e); Quantity: 58
  • Bored pile: Diamater: 0.8(e); Depth: 46.5(e); Quantity: 58
  • Employer
  • Space 21 Fonexim